New York Court of Appeals
Sisters of Saint John the Baptist, Providence Rest Convent, Respondent v. Phillips R. Geraghty Constructor, Inc…
May 8, 198667 N.Y.2d 997
Summary
The New York Court of Appeals held that the arbitration clause in the construction contract covered the dispute over extra work and cost overruns, reversed the Appellate Division’s stay of arbitration, and ordered the stay denied.