Supreme Court of Delaware
Trascent Management Consulting, LLC, Plaintiff-Below, Appellant v. George Bouri, Defendant-Below, Appellee
November 28, 20162016 Del. LEXIS 618
Summary
The Supreme Court of Delaware affirmed the Court of Chancery’s order requiring Trascent to advance Bouri’s litigation expenses under the plain language of the employment and LLC agreements. Trascent could not avoid its advancement obligation in a summary proceeding by asserting that the agreements were fraudulently induced, because that defense presented a plenary claim requiring separate adjudication and would undermine the purpose of expedited advancement proceedings. Trascent remained free to pursue its fraud and indemnification arguments in a plenary proceeding and seek recoupment of improperly advanced amounts.