Supreme Court of Connecticut

Centerplan Construction Co., LLC v. Hartford

May 24, 2022343 Conn. 368

Summary

The court reversed the judgment for the city because the trial court resolved several contract-interpretation and termination issues as a matter of law that required fact-finder determinations. It held that control and responsibility for the architect shifted over distinct contractual periods, that DoNo retained the ability to pursue certain pre-term-sheet claims, and that Centerplan retained some right to notice and an opportunity to cure before termination. The court remanded for a new trial addressing contract control, ratification, termination rights, notice and cure, and futility.